Siziano Campus - Stack Infrastructure

In permittingIT015Via Marche 8, Siziano (PV), Lombardia

IT load

71.6 MW

IT load of the whole campus.

Thermal power of generators

480 MWt

Whole campus at full build. 216 MWt is in place or in construction.

Buildings

6

3 in operation, 1 in construction, 2 planned.

Generators

81

At full build. 38 are new.

Grid connection

132 kV

A new high voltage substation for MIL08A, linked to the MIL01 substation.

Public comments close on 9 November 2026

The ministry opened the newest public consultation for the Comune di Siziano on 10 September 2026.

Development timeline

Stage of development

Grid request
In permittingSince 25 Nov 2025
Environmental clearance
Under construction
Operating

Filing record

Full environmental review (VIA). Procedure 14473

Technical review
9 Nov 2026Deadline for public comments (second republication)Termine presentazione Osservazioni del Pubblico - II ripubblicazione. Still open
10 Sep 2026New public consultation opened (second republication)Data II ripubblicazione
13 Aug 2026Deadline for comments on the new documentsTermine presentazione Osservazioni del Pubblico su ripubblicazione
14 Jul 2026New public consultation announcedData comunicazione avvio nuova consultazione pubblica
3 Jul 2026The ministry received the extra documentsData ricezione Integrazioni
11 May 2026The ministry asked for extra documentsData richiesta Integrazioni
15 Mar 2026Deadline for public commentsTermine presentazione Osservazioni del Pubblico
14 Jan 2026Public consultation openedData avvio consultazione pubblica
25 Nov 2025Application filedData presentazione istanza. Infrastructure Italia Land 2 S.r.l.

IT load by building

A building is one data center on the campus. It is not a power source.

BuildingStateIT load
MIL01In operation. Expansion24 MW
MIL08APlanned20 MW
MIL07Planned12 MW
MIL02In operation. Expansion5.6 MW
MIL03In operation. Expansion5 MW
MIL08BIn construction. Expansion5 MW
Whole campus71.6 MW

Source: Sintesi non tecnica VIA, page 17 and page 18.

Documents

DocumentKindDatePagesFile
Avviso al pubblico del 10/09/2026 per la consultazione pubblica nel Comune di Siziano3 factsPublic notice10 Sep 20262Download
Avviso al pubblico del 14/07/2026Public notice14 Jul 20261Download
Sintesi non tecnica VIA12 factsNon technical summary14 Jan 202683Download
Avviso al pubblico del 14/01/20263 factsPublic notice14 Jan 20262Download
Allegato alla Comunicazione VA esito valutazione - Parere CTVA del 06/10/20252 factsTechnical opinion5 Nov 202551Download
Comunicazione VA esito valutazioneOutcome letter5 Nov 20252Download

Downloads are for subscribers. See plans

Where the facts come from

Each fact keeps the exact words of the document. A program checks the quote before we save the fact.

FactValueExact wordsDocument
IT load71.6 MWprevede l’insediamento complessivo di circa 71,6 MW di potenzaSintesi non tecnica VIAPage 18
Thermal power480 MWtconto dei futuri sviluppi e degli ampliamenti dei siti esistenti oltre allo stato attuale, pari a 480 MWtSintesi non tecnica VIAPage 34
Buildings6per un totale di 6 unitàAvviso al pubblico del 14/01/2026Page 1
Grid cable132 kVrelativo cavo interrato a 132 kV collegato alla sottostazione di MIL01 esistenteSintesi non tecnica VIAPage 32