The European data center pipeline,built from official filings.
See where data center capacity is being built so you can plan, invest, and compete with institutional-grade intelligence.
See where data center capacity is being built so you can plan, invest, and compete with institutional-grade intelligence.
The map
We track public records, interconnection queues, regulatory filings, and data center intelligence, so you don't have to.
Grid request
3,500+
projects have asked for grid capacity.
In permitting
850+
of them have filed for a permit.
Under construction
200
projects are under construction.
Operating
2,800
data centers are in operation.
Why we built it
Land owners and developers file permits solely to lock up power allocation, artificially inflating the property's value while blocking legitimate projects.
101 GW
total grid requests in Italy
3 GW
of projects have a permit
Building your own database takes a year or more of manual work
Investors and developers cannot tell a real project from a speculative one
Public data is fragmented
Collect
We read permit procedures, environmental reviews, municipal notices and grid operator data.
Structure
Data is reconciled across sources and categorized under each project.
Analyze
Each project receives a power date, build probability, and an aggregated report.
The numbers
Many developers ask for grid capacity, few file for a permit. We count both, so you see the gap.
GW requested in Italy, 31 August 2026
Sites in Italy at each stage of development
A grid request is one request to the grid operator. 9 of the 41 projects in permitting have a strategic designation from the government.
GW of 101.36 GW in Italy, 31 August 2026
1.9%
of the requested power has reached a contract.
The database
We aggregate public records, company announcements and local news into one searchable database.
| Project | Owner | Stage | Status date | Build probability |
|---|---|---|---|---|
| MIL05Vignate (MI) | Stack Infrastructure | Environmental clearance | 30 Sep 2026 | |
| ML7 and ML8Settimo Milanese (MI) | Equinix | Environmental clearance | 21 Sep 2026 | |
| Ponte San Pietro data centerPonte San Pietro (BG) | Aruba | Environmental clearance | 21 Sep 2026 | |
| Guardamiglio data centerGuardamiglio (LO) | H.I.C. HABITARE INNOVARE COSTRUIRE S.R.L. | In permitting | 21 Sep 2026 | |
| Abbiategrasso data centerAbbiategrasso (MI) | DIGITAL MILAN 1 S.R.L. | In permitting | 14 Sep 2026 | |
| ML10 and ML11Settimo Milanese (MI) | Equinix | In permitting | 11 Sep 2026 | |
| Siziano CampusSiziano (PV) | Stack Infrastructure | In permitting | 10 Sep 2026 | |
| Rozzano data centerRozzano (MI) | TIM | In permitting | 4 Sep 2026 | |
| Rho data centerRho (MI) | Amazon (AWS) | Environmental clearance | 1 Sep 2026 | |
| Lacchiarella data centerLacchiarella (MI) | Apto | In permitting | 1 Sep 2026 |
The next milestone, power date, build probability, source documents, and more. For every project in Europe.
Solutions
Take the whole market, take one project, or put the data inside your AI assistant.
The map and a data table for every project. Filtered by stage, owner, region and IT load.
Open Market Data2One file for each campus: the owner chain, the filing timeline, the documents, and the facts.
See a sample report3Your AI assistant queries our database to pull the exact information you need, when you need it.
See how the MCP works